When (first) orbital flight?First integrated flight test occurred April 20, 2023. "The vehicle cleared the pad and beach as Starship climbed to an apogee of ~39 km over the Gulf of Mexico – the highest of any Starship to-date. The vehicle experienced multiple engines out during the flight test, lost altitude, and began to tumble. The flight termination system was commanded on both the booster and ship."
What's happening next? SpaceX has assessed damage to Stage 0 and is implementing fixes and changes including a water deluge/pad protection/"shower head" system. No major repairs to key structures appear to be necessary.
Why no flame diverter/flame trench below the OLM?Musk tweeted on April 21: "3 months ago, we started building a massive water-cooled, steel plate to go under the launch mount. Wasn’t ready in time & we wrongly thought, based on static fire data, that Fondag would make it through 1 launch." Regarding a trench, note that the Starship on the OLM sits 2.5x higher off the ground than the Saturn V sat above the base of its flame trench, and the OLM has 6 exits vs. 2 on the Saturn V trench.
Looks like we have a tentative date for the next flight! August 31st. Obviously won’t hold, but this and the FAA Mishap report finally show some movement on the paperwork side.
9:30am- There were workers inspecting the pad shortly after the test and then there was 1 lift at the top of the OLM and 1 lift up at the chopsticks overnight. 1st shift started moving equipment back in when they arrived but they haven’t started any meaningful work as of yet. A lift has also been up at one of S25’s lift points this morning.
10:10am- I thought the lack of work on the OLM might be a sign that B9 would roll during the early closure but no sign of movement yet
11:45am- Lifts going up and down to the top of the OLM
1:07pm- Workers at the SQD
1:17pm- Side wing with the work platform swings away from the SQD
3:32pm- Crane returns to the launch pad
3:51pm- Crane removes a load from the dance floor
4:10pm- Crane removes a 2nd load of what looks like scaffolding pieces
4:22pm- 3rd load lifted and crane lowers
4:31pm- Crane leaves
5:00pm- Second closure window opens. B9 remains tucked away in the mega bay.
6:22pm- SPMT’s are still sitting outside of the mega bay. I think we can safely say they aren’t going to get B9 moved in the closure window.
6:32pm- Water truck filling up the plastic barriers around the mid bay.
8:00pm- Lifts have been up and down at the OLM. Water truck continues to fill the barriers around the mid bay. SPMT’s still sitting outside the mega bay.
9:30pm- 2 lifts have been up under the right side of the OLM working (on one of the pipes?)
10:30pm- Same 2 lifts up. Have moved to the back some
Surely they'll fix them up? Or maybe they're not that confident it will get to reentry anyway. Or even if it does they want to see how damaged tiles behave. Idk, just spitballing here
Suppression system is pretty wild. It almost sounded like a static fire. Bravo, @SpaceX That was one heck of a show.
It was! It is loud, though. With the nighttime video and muted dark colors, it looked astonishing! I wish I could download it, it's so artistic ... but of course that would be copyright violation and I would never recommend that.
Zack Golden @CSI_Starbase (Nitter link) Aug 31, 2023 · 4:24 AM UTC states "They have been testing [tiles on ship 28] with a suction device to see if they would fall off. A large number of them failed the test."
Notice they filled in the heat tiles with some type of epoxy/clay instead of replacing these damaged tiles. Indicator Ship 25 probably isn't expected to survive reentry.
But they look like regular tiles to me, just with adhesive smeared around messily. Marcus House, in his weekly update at 5:31, zooms in and says, "we can see that a few surrounding tiles were damaged during the process [of adding tiles to cover lifting points], but these were to be replaced soon after this shot was taken.". At 5:44 on, he explained and showed a worker using the suction cup device: one tile passed, one pulled off.
A bit of talk about the recent static fire, where 4 engines didn't ignite. /u/warp99 stated,
There have been a lot of subsequent tests on the GSE that supplies spin up gas to the outer ring of 20 engines.
That certainly implies that the four that failed to start cleanly may have been starved of spin up gas as all outer engines started together.
With IFT1 the startup process was staggered over three seconds and three groups of engines. SpaceX are going to cut that startup time in half which likely means starting in two groups which are probably all inners followed by all outer engines.
I think that's an interesting take, and more reassuring than engine problems, which a lot of other people have assumed.
That’s very compelling, but I guess we won’t ever know. Regardless I’m happy they can try again soon, instead of having to work 2 weeks to restore the pad after each static fire.
I wouldn’t mind them spending the next few weeks just doing 5-10 static fires to make sure they got everything right.
My gut says that if raptor reliability was as poor as the static fire makes it seem then we would be seeing more signs of panic. But now I'm unsure whether any of that would be visible to us. It sure seems like they're feeling good about things, and this theory matches that.
Zack Golden @CSI_Starbase (Nitter link) Sep 2, 2023 · 3:45 AM UTC has a multi-post speculation about Super Heavy testing at Boca Chica.
I am now 95% confident that SpaceX is in the process of building not one, but two Super Heavy Static Fire Test stands. One will be located near the Suborbital tank farm, and the other will be at the Massey's test site.
These test stands are essentially mini versions of the Orbital Launch Mount. There are a few major differences though:
These stands will not have launch capability so they will be much simpler....
Because of the location of these test stands, and severe limitations on space, the method of testing engines will have to be different than how its done on the OLM. [flame trenches]
Why?
Well at some point, launches will become much more frequent. This means the OLM will be nearly always be busy preparing for the next launch....
The Orbital Launch Mount, with its new Bidet system is limited to Static fire tests of less than 10 seconds. It is truly designed for Launching Full stacks, and not for long duration tests purely due to the volume of water stored in the tanks.
The OLM is also believed to be limited to Static Fire tests with thrust values at or around 50%. This is a result of the design of the hold down clamps. Also, the skirt of the booster is likely not designed for the kind of forces it would experience if it was being held down at max thrust....
So if this speculation is true, what should we be on the lookout for?
The areas where these will be located will either be built up to accommodate a flame trench, or they will soon begin excavating large holes into the ground for this purpose.
The suborbital tank farm will likely need to be expanded in order to increase its LOX and CH4 storage capabilities. I believe SpaceX is already in the beginning stages of this massive renovation.
CH4 storage tanks will need to be added to the Massey's test site. They will also need additional GSE equipment for filling Booster COPV's. This includes Helium storage, CO2 for the engine skirt purge system.
There will likely also need to be additional water tanks installed for traditional deluge systems for both of these tests stands....
He says he'd do a video if he weren't already in the middle of two deep-dives.
u/Alvian_11 in The Other Place says that a "flame diverter/ramp" is different from a "flame trench" and that a flame diverter/ramp makes much more sense.
It's pretty incredible to look at the build and launch sites back then vs now. None of the predicted program timelines were close to right, but the progress is still really impressive.
There is a new notice to mariners, which announces “rocket launching activities” for (approximately) September 8th. The previous notice was for August 31st.
7:25am- Lifts were up most of the night and workers started to remove equipment from around the OLM.
10:04am- SQD arm swings out of the way
10:13am- Chopsticks go up
11:00am- One lift still at the pad and no sign of pressure washers yet. I also just noticed this morning that they put hesco barriers (the big dirt filled containers) in front of the container they brought over to the side of the pad the other night. Are they really thinking about leaving it there for a launch?
1:12pm- Workers removing the tarp that covers the deluge plate
1:25pm- Forklift hauling away the tarp
1:36:44pm- B9 ambient air depress vent?
1:37:49pm- Another vent
1:38pm- Grid fins tested
2:36:56pm- FireX test
2:57pm- Sheriff at the road block
3:16:34pm- Much larger FireX test
3:46pm- Adrian predicts that it will be at least 7pm cdt before a test occurs
5:06pm- OTF venting
5:18pm- Pope stack
6:16pm- OTF venting really picking up
6:37pm- OLM vent
7:25pm- OLM vent stops. Propellant loading should be under way. Appx 30 minutes until spin prime
For context, in my relevant personal experience the FAA doesn't just receive a mishap report thrown over a wall at them. They are read into the investigation and findings and corrective actions all along the way and not surprised. So I would disagree with the word "nuts."
in describing sending the FAA the report on August 16 and immediately getting a Notice to Mariners for August 31.
The poster also doesn’t recognize that the FAA typically doesn’t issue a bunch of corrective actions in these cases. They often approve or comment against the self identified corrective actions.
Generically speaking: In all the Aerospace investigations I’ve worked on, corrective actions don’t start only when a report is issued. They start on Day 1.
Boat #SpaceX used for ops during first orbital flight test is inbound to #Starbase atm. The former GLADYS D had been offgrid last three weeks around Pensacola FL. #SpaceXArmada
... a passenger fastboat by trade, appears she's been outfitted w/ some extra gear. Worked LZ/recon ops during first orbital test flight. Now mooring in Port Isabel Texas. (@jessica_kirsh cam) piped.video link that doesn't work for me
Kevin Mock @kevmk04 replied,
The GLADYS D's sister ship was used on the first Dragon recovery mission. The GLADYS S
I can't really find full confirmation of that. I do find an Xmission from Gav Cornwell @SpaceOffshore Apr 20, 2023 · 10:54 AM UTC,
Fast boat Gladys S departed from Port Isabel this morning to support the SpaceX launch.
Still not exactly sure what role the vessel is playing but it's confirmed to be involved based on its AIS designation of 'Texas Launch' and the fact it has two Starlink dishes mounted...
Things seem to be progressing, also on the paperwork front.
Wonder when S25 moves to the launch site. Expected this to happen the last few days. Will they do a full stack, WDR, unstack, FTS, restack? They might be preparing the FTS now to avoid a restack — I guess that’s how it works for Falcon as well.
8:00am- You’ll never believe it but work continued on the staircase and top of the OLM overnight. The crane never extended and no lifts went up to the chopsticks.
8:26am- Concrete pump truck up over on the backside of the deluge tank farm
8:51am- Lift up at the back side of the chopsticks carriage
9:05am- There are 4 lifts up at the staircase. They are really pushing to finish the welding
10:43am- B10 on the move down Remidos
11:53am- B10 turns on to hwy 4
12:07pm- B10 turns into the production site
12:18pm- Turns into the megabay
1:21pm- Crane leaves OLM area
1:35pm- Concrete truck arrives to start pouring at edge of pad (5 trucks yesterday so this is number 6)
3:56pm- Small concrete mixer under the OLM. Looks like they are repouring the fondag that was removed
5:45pm- Forklift has brought in 4 pieces of metal trough(think house gutters) and placed them in the area where the concrete was poured the last 2 days.
7:21pm- Pad appears to be clear and the pope stack just started venting. Testing something tonight? BQD hood is still open right now
7:32:12pm- Purge vent from the deluge tank farm
7:49pm- Pope stack stops
8:12pm- (20:12) Rover 2 - Security at the entrance to the pad leaves. So pad should be back open.
8:16pm- Or maybe not. Pope stack starts back up
8:18pm- Recondenser vent going
8:25:25pm- More loud venting (from recondenser?)
8:57:26pm- Vent finally dies out/recondenser stops
8:58pm- Pope stack starts again
9:20pm- Fireworks
9:40pm- Half of tent 2 goes down
10:39pm- Workers return to the OLM and get right back to work on the staircase.
Long duration test fire of Raptor while gimbaled 15 degrees
Lots of discussion about why there was such a test. Some suggesting that it was for Starship for hot staging. Others saying that the new hot-staging ring has such a high dome in it that the sea-level engine gimballing so far wouldn't actually help.
Some comments about how 15 degrees is really high, like Saturn V first stage having 5 degrees, and 3-8 is more common. The Space Shuttle has 12.5 for the RS-25, but the new ones are certified for only 6. The suggestion was that this is because the stages need to be able to flip.
6:20am- The wooden concrete forms are being removed from the area around the edge of the pad
8:30am- Lifts were up at the staircase, top of the OLM, and chopsticks overnight. The air handling units were also removed from around the base.
9:40am- Area around the pad is being cleaned out of lifts and equipment. Are we in for more testing?
10:50am- Party on top of the OLM and 1 lift up. (I count at least 10 people) They did a quick run through with the sweeper
10:52am- Lift at S25. Finishing the tile work?
10:57am- Pressure washing. That’s a sure sign that we are getting ready to see the deluge
11:02am- Workers climbing into the BQD
12:00pm- Workers working on both sides of the BQD as well as on the BQD itself. (Even with RGV’s pictures I still can’t figure out what they are doing off to the sides). Pressure washing continues underneath
1:25pm- Looks like 2 pressure washing trucks are all that is left at the pad
1:28pm- Trucks leave. Still people on top of the control bunker for the tank farm
1:46pm- 3 people on the very top of the tower at the pulley for the chopsticks and a drone watching them. (NSF on the raptorside thinks they were working on the cameras)
2:28pm- Pressure washing truck back under the OLM
3:00pm- Water truck and a sweeper vehicle back at the launch site.
3:12pm- 3 people on top of the OLM. Another pressure washing truck returns
4:19pm- Pressure washing trucks leave again
5:10pm- Lift up at the deluge tanks
5:34pm- Workers taking down tarp that was set up on top of the new deluge tank
6:06:51pm- PA announcement- Clear the pad deflector testing
6:43pm- Chopsticks rising
7:28pm- Elevator just went up to the chopsticks level.
7:35pm- Last tanker truck leaving deluge tank farm
8:18pm- Another water tanker arrives at the deluge tank farm. Pad still clear
8:34pm- Tanker leaving
8:44pm- PA announcement/Klaxon
9:07pm- System is being primed
9:09pm- Whoosh
9:10:05pm- End of test (Looking at the replays, it looks like full pressure for around 25 seconds)
6:14am- Lift goes up because not even a landfalling tropical storm can stop work on the staircase
7:15am- Lift goes back down
7:26am- Lift goes back up. More workers showing up under the pad
7:44am- Second lift goes up
10:05am- 2 lifts have been up at the OLM and 1 at the chopsticks. Crane is in position to lift the kettle boiler. B9 still tucked away in the mega bay as the rain continues to fall
According to Musk Sep 6, 2023 · 1:30 AM UTC, "Starship is ready to launch, awaiting FAA license approval".
But an Other Place comment from u/space_rocket_builder here was
Aiming for launch readiness as early as next week and the launch as early as start of mid September. FAA process expected “soon” but we could still be a few weeks away.
I think they've asserted themself to be a good source, but I am not sure.
Another comment (someone else) asserted that the propellant farm has not been loaded yet, and that takes a lot of trucks.
I think right after the last static fire, u/space_rocket_builder correctly predicted the number of engines that were lit up and ran correctly, before we got an official statement. So at least, there is that.
I agree with other people regarding Musk's statement about Starship readiness: he's probably trying to pressure the FAA into giving a launch license as soon as possible. But that doesn't mean SpaceX is actually ready to launch.
10:49pm- Equipment being loaded on to the dance floor
2:31am- RIP tent 1
2:41am- Dance floor is being lifted. They didn’t raise it all the way up though.
3:33am- Dance floor stand rolls away
6:47am- Railing around the dance floor is up
7:02am- Welding tanks brought in
10:13am- Crane arrives in between the tower and back of the OLM
10:35am- Crane connected to something behind the doghouse.
10:40am- Lifts have been up inspecting all around the OLM. All of the welds on the staircase were checked. Workers have also been on top of the OLM. Vehicles have blocked the view of under the OLM all night.
11:07am- Crane lifts a flat metal rectangular frame to the backside of the OLM
11:16am- Lifts object up to the top back of the left chopstick (Maybe some kind of handrail?)
2:20pm- 3 lifts have been up at the pad and 1 at the chopsticks
3:02pm- Lift goes up to the back right chine
3:19pm- Stair section lifted into the new mega bay
6:20pm- 4 excavators are going to town clearing up the remains of tent 1
7:43pm- Crane lifts a similar piece of railing as earlier up to the right chopstick
9:40pm- Lifts still up at the OLM and chopsticks
11:32pm- Looks like 6 more beams still to be cut out before we may see an attempt at pulling the mid bay over.
Rover 1-
20:35- There is a sheriff at the entrance to the production site and sparks are flying at the front of the mid bay. Is it finally time?
22:20- Several beams have been removed on the side closest to Rover 1
7:00am- One lift was up at the OLM overnight. It changed places a couple of times but mainly at the top.
7:39am- S26’s SPMT’s leave the launch site
7:50am- Lift goes up to the back side of the tower
9:06am- Lift up disconnecting S26 from the lifting squid
9:33am- Squid disconnected and swung away
11:44am- A couple of mini excavators are working in between the OLM and OLT. At least one has a Jack hammer attachment. Breaking up more fondag?
2:35pm- LR11000 moves back over near the deluge tank farm
3:36pm-Spreader picked up by the LR11000. Prepping to move the 3rd tank in position
4:05pm- Spreader swung over to the deluge tanks
4:20pm- Spreader lowered down closer to the 3rd tank
5:03pm- Lowered down the rest of the way and lift goes up to attach the straps
5:15pm- Straps hooked up
5:25pm- Tension on the straps
7:00pm- Tank is still hooked up to the crane. Hard to tell through the heat haze if they’ve moved the tank or not. Definitely didn’t lift it very much if they have.
7:22pm- Crane lifts something about 1/3rd of the way up the backside of the tower and a lift then goes up to the same area.
9:00pm- Straps around the 3rd tank remain under tension. The OLM is quiet.
10:00pm- Sheriffs ready for road block. Looks like a stand is coming to the production site from Massey’s
10:50pm- Deluge tank is finally airborne
10:56pm- Deluge tank lowered, final adjustments still being made
11:06pm- Finally a good view of the booster stand heading down Hwy 4 to the production site
10:45pm- Crane removes a piece manifold at the deluge tank farm
11:52pm- Crane removes another big chunk of the manifold from the deluge tank farm
2:48am- Forklift removes one of the light towers from around the OLM
2:54am- LR11000 picks up the lifting squid
8:58am- Crane lifts another beam up to the new mega bay
9:44am- S26 starts rolling
9:49am- Pauses at the entrance to the rocket garden
9:51am- Turns on to Remidos
10:05am- Turns on to Hwy 4
10:35am- They aren’t taking any chances today. Have an extra power pack for the SPMT’s and a forklift in the motorcade.
11:20am- Turns into the launch site
11:33am- Arrives at the sub orbital pad
11:57am- Squid lowers to just above S26
12:12pm- Lift goes up to connect the squid
12:51pm- Squid connected. Lift goes down
2:45:52pm- Ignitor test at the OLM
2:55pm- Chopsticks release S25 and open a bit
2:57pm- Chopsticks lower a few feet
3:02pm- Chopsticks open wide and lower to their launch position
3:15pm- Chopsticks raise back up and close part way again
4:46pm- Lift up at the nosecone of S20 at the rocket garden. (Reinstalling lift hooks so it can be lifted and scrapped? Or practicing installing tiles on nosecones?)
5:22pm- S26 lifted off its transport stand and swung over to pad B
5:37pm- Making final adjustments to get it lined up on the pad
7:39am- Staircase section lifted into the new mega bay
7:47am- Excavator with metal shears attachment starts tearing the siding off the mid bay
8:45am- 3 lifts were up and down from the OLM overnight
12:10pm- The 1st shift OLM crew seem to have taken the day off.
12:40pm- You can see orange dots spray painted on some of the beams of the midbay. Indicating where to cut?
2:15pm- One lift went up to the OLM and chopsticks for a bit.
2:31pm- Workers up at the BQD in a aerial work platform
2:50pm- Workers at the BQD working on the methane and oxygen fill lines and taping over the openings. Was weird, looked the lines had been completely disconnected from the plate and that they just reached thru the holes and pulled them back out and then taped them.
5:00pm- Worker up in a lift at the mid bay using a torch to cut some of the siding to expose the support beams more
6:09:48- Vent at the pad
6:13:25- BQD venting (So much for that tape job earlier)
7:30am- Lots of welding on the staircase overnight. One lift was up at the dance floor and some welding flashes could be seen coming from there as well.
8:25am- Kettle boiler is lifted off a truck and sat on the ground on the lox side of the OTF
8:28am- 2nd kettle boiler arrives
8:38am- 3rd kettle boiler arrives
8:48am- Starlink box is on the move. Looks like it’s going to a storage area
9:08am- Second kettle boiler lifted off it’s truck
9:18am- Staircase section lifted into the new mega bay
9:28am- Kettle boiler lifted up on to it’s concrete base
9:48am- Second kettle boiler lifted up on to it’s concrete base
10:04am- Paint crew painting the new door on the OLM
10:25am- Staircase is getting a paint job as well
10:32am- Third kettle boiler is lifted up behind the first kettle boiler in the line starting a second row
1:03pm- Lift up at the tower (Looks like it’s inspecting the back right rail)
2:25pm- 2 more lifts up painting the OLM legs
4:28pm- The kettle boilers have been removed from their concrete stands
4:33pm- Worker on the SQD arm
4:42pm- Removing fence wreckage
5:51pm- Lift up to the chopsticks
8:25pm- Handrail like structure that was lifted up to the right chopstick a couple of days ago is removed. A worker is also grinding on the chopstick
8:06am- Cleaning up debris from IFT-1 around the pad
9am- Lifts were up under and on top of the OLM overnight. Lifts were used to bring equipment up to the top of the staircase. Work on the chopsticks continues as well.
And with that, I’m off to take advantage of the long weekend by taking a quick vacation with the family.
2:11am- Crane lifts another piece of bracing up to the top of the staircase
2:33am- Crane disconnects from brace.
3:11am- There is some welding happening around the pivot point of the chopsticks
3:19am- Another piece of bracing is lifted
3:56am- Crane disconnects
8:40am- Work continues on the top of the OLM near the BQD. Welders are working on the staircase. A mini excavator worked along the edge of the pad closest to the OTF most of the night.
9:45am- The reconfigured LR11000 at the build site is being raised
10:05am- Another piece of bracing is lifted up to the staircase
1:38pm- Yet another piece of bracing is lifted up
2:26pm- More bracing lifted. ( Instead of building a framework to weld the shielding on to at the top of the staircase. They welded the shielding to the OLM and are now building the structure to support it. )
3:09pm- The LR11000 at the build site finishes raising into its new configuration
3:25pm- Concrete truck arrives to pour into the new forms along the edge of the pad
3:50pm- Another piece of bracing lifted up (That’s 11 pieces)
4:15pm- Roof panel lifted up to the staircase. Concrete truck count at 3
5:23pm- Chopsticks raising
5:33pm-Chopsticks lowering (must be testing some of the work they’ve done)
7:54pm- End panel being removed from tent 2
8:05pm- End panel partially collapses
8:16pm- End panel ripped down. Definitely not trying to save it
8:30pm- Looks like another piece of bracing lifted to the stairs. (In a small box on SBL so I might be wrong but something was definitely lifted to the top of the stairs)
8:57pm- Awesome raptor test at McGregor
9:13pm- SPMT’s headed to Masseys
10:06pm- Hot stage ring being lifted up in the megabay
8:30am- Lifts were up to the top of the OLM and chopsticks overnight. A crane was also extended to the chopsticks but never lifted or lowered anything. So probably just support for whatever was being worked on. Paint crews are at work currently on the cryo leg. No lifts have gone up to the staircase in over 24 hours.
10:50am- Crane goes back up to the chopsticks
1:25pm- Literally watching paint dry. Lift has been up at the BQD as well.
2:00pm- Lift goes back up to the right rear chine. Hopefully someone will get a ground shot of what they’ve been doing because you really can’t tell on the video
3:00pm- Aerial work platform goes up near top of B9 and then starts coming down. Stopped at chopsticks
3:08pm- Stair section lifted into the new mega bay
3:48pm- Crane lifts part of the moveable rails (tank treads) on the left chopstick. Shifts it backwards
4:12pm- The LR11000 at the pad is on the move
4:36pm- LR11000 stops by deluge tank farm. Crane lowers from the chopsticks
10:05pm- Lots of workers have been walking around the top of the OLM. A scissor lift has been up under the piping to the left side of the staircase. Work also continues on the chopsticks with lifts going up and down. An aerial work platform is up by the back right rail on the tower that was inspected a few days ago. Finally a lift is up at the staircase and all is right in the world again. (Even though it looks like they just used it to lift equipment up to the doorway and they aren’t actually working on the staircase)
I'm actually kind of shocked by how useless and jokey most the comments are on that reddit post. Did the main sub change policies at some point? That seems worse than an old lounge thread.
(Note: at 6 pm ET on Wednesday, the FAA issued the following statement).
"The SpaceX Starship mishap investigation remains open," the agency stated. "The FAA will not authorize another Starship launch until SpaceX implements the corrective actions identified during the mishap investigation and demonstrates compliance with all the regulatory requirements of the license modification process."
11:45pm- Booster stand arrives at the production site. Goes in to the fenced in yard where the mid bay was.
3:10am- Deluge tank lifted again
3:25am- Tank is sat back down
9:40am- Deluge tank is still hooked to the load spreader and under tension. No lifts were up at the OLM overnight but workers could be seen going up and down the stairs.
10:51am- Straps unhooked from the deluge tank
11:48am- Concrete truck at the pad. Looks like they are pouring something off to the side of the pad.
12:33am- 2nd ventilation hose installed to the OLM
6:45am- Forklift moves a header tank to over by the HLS nosecone
7:36am- AWP goes back up to the SQD arm
8:00am- Lots of welding on the staircase shielding overnight. A few lifts went to the top of the OLM
10:29am- Workers up at the SQD
10:44am- SQD arm getting a fresh coat of paint as well
10:45am- Crane lifts a cross brace up to the halfway point of the staircase. (Piece of square steel tubing)
11:29am- Crane lifts another cross brace up to the staircase. A little above the first one
11:52am- Concrete forms being built around the edge of the OLM pad
1:40pm- 2nd vent hose lowered about halfway. (Probably getting in the way of the welders working on the staircase)
1:51pm- Crane lifts the next cross brace up to the stairs.
3:04pm- S29 rolls out of the high bay
3:10pm- Next cross brace lifted up to the staircase
3:54pm- Another cross brace lifted
4:29pm- After rotating a bit, S29 rolls back into the high bay
5:39pm- Venting at the production site. Can’t see it on Rover 1. Raptor roost definitely shows it at the production site though. Not sure what it is from.
6:45pm- Another piece of bracing is lifted. This one will support the top of the shielding on the right hand side